The usable and gross floor area schedule: the most common mistakes

The usable area in a valuation, the one on the energy certificate and the cadastre’s gross area are not measured the same way. Countable area is set by each municipality. That is why a schedule has to say which criterion it uses.

1.50 mThe height that most often makes usable area differ from one document to another.
In this article
  1. The short version
  2. One word, several definitions
  3. Usable area: what is measured inside
  4. Gross area: what is measured outside
  5. The same flat, four figures
  6. The mistakes that recur
  7. How to build a clear schedule
  8. Where Archelo helps

The short version

The area schedule looks like the simplest part of a project and is one of the parts that gets reworked most. It is redone every time a room changes and copied into the report, the drawings, the planning sheet and the energy certificate. One copy falling behind is enough for two documents to show different figures, which is hard to spot. The rules cited are Spanish.

One word, several definitions

Annex I of Part I of the building code requires the descriptive report to set out the «geometry of the building, volume, usable and gross areas, access and evacuation». It marks this as basic-project content. It does not say how the areas are measured. The definitions a practice works with come from rules written for other purposes:

RuleWhat it definesWhat for
Order ECO/805/2003, art. 4Usable area. Gross area without and with common partsValuations for financial purposes (mortgages)
Royal Decree 390/2021, art. 2.tUsable areaEnergy performance certificate
Royal Decree 1020/1993, rule 11.3Gross areaCadastral value
DB-SI, annex AUsable area: the area people can occupyOccupancy calculation
Local plan or municipal bylawCountable or built floor areaBuildability and the other planning parameters

None is «the right one» in the abstract. Each is correct for its own purpose. The mistake appears when a figure calculated under one criterion is used to justify something governed by another.

Usable area: what is measured inside

Order ECO/805/2003 defines usable area as the floor area bounded by the inner face of the external walls. It leaves out what is taken up by fixed internal partitions, vertical structural elements, service runs or ducts over 100 cm² in horizontal section and floor with a clear height under 1.5 m. Outdoor spaces are not usable area.

Royal Decree 390/2021 repeats those exclusions almost word for word, with one important difference: it adds half the area of covered private outdoor spaces, measured on the horizontal projection of their roof. Uncovered ones stay out. So the usable area on the energy certificate of a flat with a covered terrace is not the usable area in its valuation.

The building code uses usable area for calculations. DB-SI occupancy comes from table 2.1 in section SI 3 «based on the usable area of each zone». The window of a habitable room under DB-HS 3 must have an openable area of at least one twentieth of its usable area. A measuring mistake here is not a formatting issue: it changes a justification.

Gross area: what is measured outside

Under ECO/805/2003, gross area without common parts is usable area without deducting internal elements and adding the external walls. Facade and party walls count at 100%. Walls shared with other units in the same building count at 50%. Gross area with common parts adds the share of common elements set by the unit’s quota. Since it starts from usable area, terraces stay out.

The cadastre measures differently. Rule 11.3 of Royal Decree 1020/1993 takes the area inside the outer line of the perimeter walls and the centrelines of any party walls. It deducts lightwells. Covered balconies, terraces and porches count at 50%. If closed on three of their four sides, they count at 100%. In residential use, spaces under 1.50 m high do not count.

DB-SI, for its part, limits fire compartments by gross area: in residential dwelling use, no compartment may exceed 2,500 m² (section SI 1, table 1.1). Measurement has consequences here too. How the report should state it is covered in what a project report must contain.

The same flat, four figures

An illustrative example: a two-bedroom flat with 57.60 m² of usable area by room, 68.90 m² gross without the terrace and a covered terrace of 6.00 m², open on two sides.

FigureCriterionTerraceResult
Usable, for valuationECO/805/2003Not counted57.60 m²
Usable, for the energy certificateRD 390/202150%: 3.00 m²60.60 m²
Gross without common partsECO/805/2003Not counted68.90 m²
Gross, cadastralRD 1020/199350%: 3.00 m²71.90 m²
CountableThe council’s bylawWhatever the bylaw saysUnder its article

The example simplifies: in practice the cadastral and valuation gross areas also differ in how party walls and facades are measured. But it is enough to show the problem: four correct figures for the same flat. If the schedule does not say which is which, the officer reading the report and the certificate will see two different numbers with no reason given.

The mistakes that recur

Real applications keep showing schedules that do not hold up on their own:

  • The rows do not add up to the total. A room was added or deleted on the drawing and never reached the table. Or the total was typed by hand.
  • Report and drawings say different things. The drawing’s schedule was updated and the report’s was not. Or the other way round.
  • The same room under two names or with two areas in the same document.
  • No criterion stated. Nothing says whether usable area includes the terrace or which bylaw article governs the countable area.
  • Countable area calculated as gross area. The exclusions or percentages the local plan sets for basements, attics, projections or terraces are not applied.
  • Inherited figures. An area from an earlier version survives in the planning sheet, the energy certificate or the parking justification.
  • Rounding that does not add up. Rooms are given to two decimals and the total, rounded to the unit, is no longer the sum.

In the retail-to-residential change of use we reviewed, the report’s schedule included a room that was not drawn, left out another and did not add up to the total it stated. The drawing did.

How to build a clear schedule

A sound schedule has few rules and keeps all of them:

  • A single source. Areas come from the drawing or the model. The report copies them from there, never the other way round.
  • Usable area by room, gross area by floor. Each total shows how it adds up.
  • Countable area kept apart, with the bylaw article that sets what counts and how. It is compared with the maximum buildability.
  • A criterion note under the schedule: which rule each column follows and how terraces, low spaces, lightwells and party walls are treated.
  • The same room names in the schedule, on the drawings and in the DB-SI and DB-HS justifications.
  • In a refurbishment, existing and proposed states under the same criterion, so the difference can actually be read.

Before submission, one last pass:

  • Every row adds up to its floor total and the floors add up to the building total.
  • Usable, gross and countable areas show the same figure in the report, drawings, planning sheet and parking justification.
  • The energy certificate’s usable area is calculated under RD 390/2021 and, if it differs from the report’s, the reason is given.
  • DB-SI occupancy and DB-HS 3 windows start from the usable areas in the current schedule.
  • The criterion note cites the bylaw that governs countable area.
  • No figure from an earlier version is left in any document.

The cross-check of the rest of the application is explained in documents for a building permit application.

Where Archelo helps

Archelo measures on the drawings when the file allows it, such as a DXF or a PDF with layers. From those measurements it builds the schedule: rooms with their usable area, grouped by floor. It then cross-checks those figures with the report and the estimate. It flags what does not match, with the document and page of each figure: rows that do not add up, rooms missing or extra, different areas for the same room. The countable-area criterion depends on each council’s bylaw and stays with the practice, as does the final measurement. You can see how it works on AI for architects.

This article is for information only and does not replace checking the current text of the rules cited, nor each council’s local plan and bylaws, which set how countable area is measured.

Keep reading

10 · 3 · 1The years of liability for structure, habitability and finishes, counted from handover.LOE, art. 17.1

The Building Act in a practice: who answers for what and from when

Each party answers for its own part for ten, three or one year depending on the defect. Every period runs from handover, so a badly closed handover record moves the clock and leaves parts uncovered.

Ground floor plus one, seven to twelve dwellings upstairsThe decree requires the lift installed. The building code settles for leaving room for one.

Accessibility in Andalusia: Decree 293/2009 in housing projects

In a residential building, Decree 293/2009 governs communal areas and reserved dwellings, not the inside of the others. It applies alongside DB-SUA. Where the two differ, the stricter one must be met.

Art. 299.2Other authorities’ approvals come before the permit. A permit cannot be conditional on obtaining them later.LISTA Regulations

How to organise a project application before you submit it

A well-organised application prevents a missing document, an invalid signature or two figures that disagree. The council’s own list is the one that counts. Documents are sorted by when they go in: with the application, before work starts or at completion. Before signing, the same figure has to read the same in every document.

Four jobs that must be certified
  • Execution project
  • Final certificate
  • Legalisation
  • Demolition without explosives

Visado: when certification by the professional body is mandatory

Certification by the professional body is voluntary except for a closed list of work. In building, the list includes the execution project and the final certificate. The basic design is not on it and a permit can be applied for with it.

AI for architects: can it check a project against building regulations?

Software can already verify much of what a project has to state, with the article and page of every figure. What it cannot do is decide what your project means. And nothing failing does not mean it complies.

€450,759.08The contract price, with VAT, from which the study must be the full one.RD 1627/1997, art. 4.1

The basic health and safety study (RD 1627/1997): when it is enough and what it contains

Every project-based job carries a health and safety study, full or basic. Four conditions decide which. The cost threshold is measured on the contract budget with VAT, not on the material execution budget.

Seven minimum contents
  • Estimate and prevention
  • Destination and separation
  • Drawings and specifications
  • Cost

The construction waste management study (RD 105/2008): what it must include

RD 105/2008 requires the waste management study and the designer writes it. It has seven minimum contents and five of them already go in the basic design. A refurbishment adds an inventory of hazardous waste.

ChatGPT for architects: what it is good for, where it fails with regulations and how to check it

ChatGPT and the other general assistants draft, summarise and explain well. They are not a source of regulations: use them for the former and never accept a requirement without opening the official text.

Documents for a building permit application in Spain: the complete file, in order and reviewed

A permit application with a project brings together five groups of documents. Each council publishes its own list, though the core is common across Spain. Before submitting, the most useful check is that they all say the same.

Art. 138What goes by self-declaration in Andalusia. Everything else needs a permit.LISTA

Self-declaration or building permit in Andalusia: when each applies

In Andalusia the permit is the rule and the self-declaration the exception listed in article 138 of the LISTA. Needing a project does not mean needing a permit: a refurbishment with a project on urban land can go by self-declaration if it leaves occupancy, height, buildable area and number of dwellings unchanged.

DB-SUA in housing: stairs, guarding and changes of level

The stair in a duplex and the communal stair are not justified with the same figures. Their balustrades are: the conditions against climbing and openings are the same throughout the building.

Refurbishment or maintenance?The first thing that decides which part of DB-SI must be justified.

DB-SI in a dwelling refurbishment: what to justify and what not

In a refurbishment DB-SI neither applies in full nor stops applying. It reaches what the work alters, escape routes if occupancy changes and protection systems if what carries them is touched. Existing safety can never be made worse.

50 l/sThe minimum extraction over the hob, with its own duct.CTE DB-HS 3

DB-HS 3: how to justify a dwelling’s ventilation rates

Table 2.1 gives the flows and the justification does not end there. Supply and extract must be balanced, openings and ducts sized and the kitchen solved. A two-bedroom flat shows how.

What a project report must contain under Spain’s building code and how to review it before submission

The report is where a project is justified. Spain’s building code sets its minimum content. What must be written depends on the work, the use, the stage and the council.

Is it allowed? Does it comply? Does the building permit it?The three questions of a shop-to-dwelling change, in order.

Retail to residential: what to check before applying for the permit

Changing a shop’s use is work that needs a project, however small it looks. The first question is not the building code but the plan: if housing is not allowed on that floor and that street, no project will do.

How to use AI in an architecture practice: from brief to permit

When people talk about AI for architects they almost always mean images. But a project is a long chain, from brief to permit. Each stage has work you can delegate and work you cannot.

40% · 20%The national minimum reserve: on rural land being urbanised, and on urbanised land under renewal.TRLSRU, art. 20.1.b

Affordable housing reserve: what to check before fixing the percentage

The national Land Act sets a minimum of 40% or 20% depending on the development. Regional law, the current plan and transitional provisions can change that figure on each site.

Pilot programme

Try Archelo on a real case.

Archelo helps you prepare all your project documents, analyses the drawings, tells you whether it complies before you submit and keeps everything organised. Want to try it?

Watch the demo

Request access

Try Archelo on your own projects. Fill in the form and we will email you as soon as your access is ready.

We use these details only to give you access.