DB-SUA in housing: stairs, guarding and changes of level

The stair in a duplex and the communal stair are not justified with the same figures. Their balustrades are: the conditions against climbing and openings are the same throughout the building.

In this article
  1. The short version
  2. Restricted or general use: the first question
  3. The stair inside the dwelling
  4. The communal stair
  5. Changes of level: when guarding is needed
  6. What the balustrade must be like
  7. In a refurbishment or change of use
  8. What to write in the report
  9. How Archelo handles it

The short version

Stairs and guarding can go wrong for the same reason: the figures for a general-use stair are applied to the stair inside a duplex or a dwelling’s figures to the communal stair. We follow section SUA 1 of the Basic Document SUA (safety in use and accessibility) in its consolidated version of 14 June 2022, the Ministry’s annotated edition of 15 July 2024 and, for the strength of balustrades, DB SE-AE on actions. The rules are Spanish. The split between private and common stairs will be familiar from most codes.

Restricted or general use: the first question

Annex A defines restricted use as circulation areas or elements limited to at most 10 regular users. The definition includes «the inside of dwellings» and excludes the common areas of residential buildings. The Ministry’s comment leaves no room for argument: the inside of a dwelling is always restricted use, however many people live there. The common areas never are.

The common areas are the communal stairs, landings, entrance halls, car parks and corridors to storage rooms. And since annex A’s definition of public use does not mention residential use, they are general use but not public use. That difference decides the maximum riser.

The stair inside the dwelling

The stair in a duplex, a penthouse with a study above or a single-family house is restricted use and follows SUA 1 section 4.1, far shorter than the general-use rules:

  • Each flight at least 0.80 m wide, which according to the Ministry’s comment must be kept along the landings too.
  • Riser of 20 cm at most and going of 22 cm at least, measured in the direction of travel and without the projection of the step above.
  • On curved stairs, the going is measured on the centre line if the stair is under 1 m wide and 50 cm from the narrow side if wider. It also measures at least 5 cm on the narrow side and at most 44 cm on the wide side.
  • Split landings with 45º winders and open risers are allowed, with the treads overlapping by at least 2.5 cm.
  • A balustrade on any open side.

The Ministry adds two clarifications. Mixed stairs, with straight and curved flights, are accepted for restricted use too. Alternating-tread stairs, the «ship» or «samba» type, are never valid. Inside the dwelling neither the 2R + G rule nor the minimum of three steps per flight applies: both belong to section 4.2.

The communal stair

The communal stair is general use (section 4.2) and here almost everything counts. The table sums up what it asks for in a residential building, depending on whether a lift is available as an alternative:

ConditionWith an alternative liftWithout an alternative liftClause
Clear width of flight1.00 m1.00 mSUA 1, table 4.1
Going on straight flightsAt least 28 cmAt least 28 cmSUA 1, 4.2.1
RiserBetween 13 and 18.5 cmBetween 13 and 17.5 cmSUA 1, 4.2.1
Going and riser together54 ≤ 2R + G ≤ 70 cm54 ≤ 2R + G ≤ 70 cmSUA 1, 4.2.1
Maximum rise of a flight3.20 m2.25 mSUA 1, 4.2.2
HandrailsOne side if it rises more than 55 cm. Both if wider than 1.20 mBoth sides, extended 30 cm at the ends on at least oneSUA 1, 4.2.4

Nosings are not allowed and every step between two floors has the same riser. Landings are at least 1 m long on the centre line and handrails sit between 90 and 110 cm high. For a lift to count as an alternative, the Ministry explains, it need not be next to the stair nor be accessible: it is enough that users can use it as such in normal conditions.

A worked example

An existing residential building without a lift, 3.00 m floor to floor. With 17 risers each would be 17.65 cm: too high, since without a lift the maximum is 17.5 cm. With 18 risers of 16.67 cm and a 28 cm going, 2R + G = 61.3 cm, within range. And as a flight cannot rise more than 2.25 m, each floor takes two flights of nine steps, 1.50 m each, with a landing between.

Changes of level: when guarding is needed

Section 3.1 requires guarding at changes of level, holes and openings, horizontal or vertical, balconies and windows, where the drop exceeds 55 cm. Exceptions apply where the construction makes a fall very unlikely and where a barrier is incompatible with the intended use. For the first, the Ministry mentions planted areas or water features. Its comment says this does not work where unsupervised children can be expected, which in housing all but rules it out.

What the balustrade must be like

Here is the exception that is easy to forget: section 3.2.3 applies its conditions «anywhere in residential buildings», stair and ramp balustrades included. The balustrade in the duplex meets the same rules as the one in the communal stair.

ConditionRequirementClause
Height0.90 m if the drop is no more than 6 m and 1.10 m otherwise. At stair wells narrower than 40 cm, 0.90 m. Measured from the floor or, on stairs, from the pitch line of the stepsSUA 1, 3.2.1
ClimbabilityNo footholds projecting more than 5 cm between 30 and 50 cm high and no horizontal surfaces deeper than 15 cm between 50 and 80 cmSUA 1, 3.2.3 a)
OpeningsA 10 cm sphere must not pass. The triangle between step and balustrade is excepted if its bottom edge is no more than 5 cm from the pitch lineSUA 1, 3.2.3 b)
StrengthThe horizontal force in DB SE-AE table 3.3, applied at 1.2 m or at the top edge if lower. That is 0.8 kN/m in general cases and 1.6 kN/m for categories C3, C4, E and F. For C5, 3.0 kN/mSUA 1, 3.2.2 and SE-AE, 3.2

According to the Ministry’s comment, the risk is a child under six climbing over and falling, so climbability also covers fixed elements less than 50 cm from the guarding, such as a radiator. And although the gap between slab edge and balustrade is treated as a 10 cm opening, good practice advises keeping it to 3 cm.

A window is just another opening: if the sill is below guarding height and the drop exceeds 55 cm, it must be protected (figure 3.1).

In a refurbishment or change of use

In a refurbishment that keeps the use, the document applies to the elements the work alters, where that improves them. Existing conditions can never be made worse (rules 3 and 4 of section III). Rebuilding a stair inside a flat or replacing a balustrade means doing it to the document. Leaving an old building’s communal stair untouched does not.

Where compliance is not technically or economically viable or clashes with the building’s protection, alternative solutions may come as close as possible. Any limits on use are recorded in the as-built documentation. In a change of use, the Ministry allows flexibility where risk goes down and mentions turning a shop in a residential building into a dwelling. We cover the rest in retail to residential change of use.

What to write in the report

The justification of these clauses fits on one page if it is organised like this:

  • Which stairs there are and the type of each: restricted use (inside the dwelling) or general use (common areas).
  • Whether a lift serves as an alternative to the communal stair, since it sets the maximum riser, the rise per flight and the handrails.
  • Going, riser, number of steps, rise of each flight and clear width, with the 2R + G check on general-use stairs.
  • Drops of more than 55 cm, openings and low windows, with the height of each drop, which decides between 0.90 and 1.10 m.
  • How balustrades meet the climbability and opening rules, inside the dwelling too. Their use category for the horizontal force.
  • In a refurbishment, which elements are altered, the statement that existing conditions are not made worse and, if the document is not met, the solution adopted and why.

Common mistakes

  • Justifying a duplex stair with the 28 cm going and three steps per flight or the communal stair with the 20 cm riser for restricted use.
  • Taking an 18.5 cm riser in a building with no lift.
  • 0.90 m balustrades on balconies with more than 6 m of drop.
  • Balustrades with horizontal rails that act as a step between 30 and 50 cm. The same goes for planters and radiators next to them.
  • A report saying «general-use stair» and drawings with 20 cm risers. We discuss cross-checking report and drawings in what a project report must contain.

How Archelo handles it

Archelo shows in its regulations view the DB-SUA figures for the project’s use, each with its clause: flight width, going and riser, flights, landings, handrails, guarding height and restricted-use stairs. It also checks whether the report justifies DB-SUA. It does not measure stairs or balustrades on the drawings nor decide whether a lift counts as an alternative: the architect justifies that. What it points out is where it still needs writing down.

You can see how it works on AI for architects. This article is for information and does not replace checking the code’s text in force, regional accessibility rules or the local bylaws that apply to the project.

Keep reading

10 · 3 · 1The years of liability for structure, habitability and finishes, counted from handover.LOE, art. 17.1

The Building Act in a practice: who answers for what and from when

Each party answers for its own part for ten, three or one year depending on the defect. Every period runs from handover, so a badly closed handover record moves the clock and leaves parts uncovered.

Ground floor plus one, seven to twelve dwellings upstairsThe decree requires the lift installed. The building code settles for leaving room for one.

Accessibility in Andalusia: Decree 293/2009 in housing projects

In a residential building, Decree 293/2009 governs communal areas and reserved dwellings, not the inside of the others. It applies alongside DB-SUA. Where the two differ, the stricter one must be met.

Art. 299.2Other authorities’ approvals come before the permit. A permit cannot be conditional on obtaining them later.LISTA Regulations

How to organise a project application before you submit it

A well-organised application prevents a missing document, an invalid signature or two figures that disagree. The council’s own list is the one that counts. Documents are sorted by when they go in: with the application, before work starts or at completion. Before signing, the same figure has to read the same in every document.

Four jobs that must be certified
  • Execution project
  • Final certificate
  • Legalisation
  • Demolition without explosives

Visado: when certification by the professional body is mandatory

Certification by the professional body is voluntary except for a closed list of work. In building, the list includes the execution project and the final certificate. The basic design is not on it and a permit can be applied for with it.

AI for architects: can it check a project against building regulations?

Software can already verify much of what a project has to state, with the article and page of every figure. What it cannot do is decide what your project means. And nothing failing does not mean it complies.

€450,759.08The contract price, with VAT, from which the study must be the full one.RD 1627/1997, art. 4.1

The basic health and safety study (RD 1627/1997): when it is enough and what it contains

Every project-based job carries a health and safety study, full or basic. Four conditions decide which. The cost threshold is measured on the contract budget with VAT, not on the material execution budget.

Seven minimum contents
  • Estimate and prevention
  • Destination and separation
  • Drawings and specifications
  • Cost

The construction waste management study (RD 105/2008): what it must include

RD 105/2008 requires the waste management study and the designer writes it. It has seven minimum contents and five of them already go in the basic design. A refurbishment adds an inventory of hazardous waste.

1.50 mThe height that most often makes usable area differ from one document to another.

The usable and gross floor area schedule: the most common mistakes

The usable area in a valuation, the one on the energy certificate and the cadastre’s gross area are not measured the same way. Countable area is set by each municipality. That is why a schedule has to say which criterion it uses.

ChatGPT for architects: what it is good for, where it fails with regulations and how to check it

ChatGPT and the other general assistants draft, summarise and explain well. They are not a source of regulations: use them for the former and never accept a requirement without opening the official text.

Documents for a building permit application in Spain: the complete file, in order and reviewed

A permit application with a project brings together five groups of documents. Each council publishes its own list, though the core is common across Spain. Before submitting, the most useful check is that they all say the same.

Art. 138What goes by self-declaration in Andalusia. Everything else needs a permit.LISTA

Self-declaration or building permit in Andalusia: when each applies

In Andalusia the permit is the rule and the self-declaration the exception listed in article 138 of the LISTA. Needing a project does not mean needing a permit: a refurbishment with a project on urban land can go by self-declaration if it leaves occupancy, height, buildable area and number of dwellings unchanged.

Refurbishment or maintenance?The first thing that decides which part of DB-SI must be justified.

DB-SI in a dwelling refurbishment: what to justify and what not

In a refurbishment DB-SI neither applies in full nor stops applying. It reaches what the work alters, escape routes if occupancy changes and protection systems if what carries them is touched. Existing safety can never be made worse.

50 l/sThe minimum extraction over the hob, with its own duct.CTE DB-HS 3

DB-HS 3: how to justify a dwelling’s ventilation rates

Table 2.1 gives the flows and the justification does not end there. Supply and extract must be balanced, openings and ducts sized and the kitchen solved. A two-bedroom flat shows how.

What a project report must contain under Spain’s building code and how to review it before submission

The report is where a project is justified. Spain’s building code sets its minimum content. What must be written depends on the work, the use, the stage and the council.

Is it allowed? Does it comply? Does the building permit it?The three questions of a shop-to-dwelling change, in order.

Retail to residential: what to check before applying for the permit

Changing a shop’s use is work that needs a project, however small it looks. The first question is not the building code but the plan: if housing is not allowed on that floor and that street, no project will do.

How to use AI in an architecture practice: from brief to permit

When people talk about AI for architects they almost always mean images. But a project is a long chain, from brief to permit. Each stage has work you can delegate and work you cannot.

40% · 20%The national minimum reserve: on rural land being urbanised, and on urbanised land under renewal.TRLSRU, art. 20.1.b

Affordable housing reserve: what to check before fixing the percentage

The national Land Act sets a minimum of 40% or 20% depending on the development. Regional law, the current plan and transitional provisions can change that figure on each site.

Pilot programme

Try Archelo on a real case.

Archelo helps you prepare all your project documents, analyses the drawings, tells you whether it complies before you submit and keeps everything organised. Want to try it?

Watch the demo

Request access

Try Archelo on your own projects. Fill in the form and we will email you as soon as your access is ready.

We use these details only to give you access.