The construction waste management study (RD 105/2008): what it must include
RD 105/2008 requires the waste management study and the designer writes it. It has seven minimum contents and five of them already go in the basic design. A refurbishment adds an inventory of hazardous waste.

- Estimate and prevention
- Destination and separation
- Drawings and specifications
- Cost
In this article
The short version
The waste management study is one of those annexes passed from project to project with little more than the job name changed. And it shows quickly, because it is cross-checked against the report, the estimate and the deposit the council asks for. We follow Spain’s consolidated Royal Decree 105/2008, article 30 of Act 7/2022 on waste and contaminated soils and the European list of waste.
Who needs it and who signs it
The decree splits the duties between two parties worth keeping apart (article 2):
- Producer: the holder of the planning permit or, if the work needs none, the owner of the property. They must include the study in the project. In practice the architect writes it on their behalf.
- Holder: whoever carries out the work and physically controls the waste, meaning the contractor, its subcontractors and the self-employed. Their employees are not.
Minor domestic construction or repair works fall outside articles 4 and 5 (first additional provision) and are governed by council bylaws. The decree defines them as simple, small-scale works in a home, shop, office or service building. They do not change the volume, use, shared services or number of dwellings and premises. They need no signed project. If the work needs a project, it needs a study.
The seven minimum contents
Article 4.1.a lists what the study must contain. Article 4.2 adds that, for building works, the basic project submitted for the permit must already include items 1 to 4 and item 7, plus the hazardous waste inventory where it applies. Drawings and specifications can wait for the construction project:
| Item | What it must say | Basic project |
|---|---|---|
| 1. Estimate | Quantity in tonnes and cubic metres, coded with the European list of waste | Yes |
| 2. Prevention | Measures to produce less waste on this job | Yes |
| 3. Destination | Reuse, recovery or disposal operations for each waste | Yes |
| 4. Separation | How the streams are separated on site | Yes |
| 5. Drawings | Facilities for storage, handling, separation and other management operations | No, at construction stage |
| 6. Specifications | Clauses on storage, handling, separation and other operations | No, at construction stage |
| 7. Cost | Expected cost of management, as a separate chapter of the estimate | Yes |
The estimate’s separate chapter is easy to forget. Waste management cannot be dissolved into the demolition items or the site overheads: it has to be readable on its own, because it is the figure used for the deposit. How it fits with the other documents is covered in documents for a building permit application.
The estimate, with its codes
Construction and demolition waste sits in chapter 17 of the European list, published by Decision 2014/955/EU. Codes with an asterisk are hazardous. The table gives the usual ones in a building project, with the threshold above which article 5.5 of the decree requires them to be separated:
| Stream | Code | Separate above |
|---|---|---|
| Concrete | 17 01 01 | 80 t |
| Bricks · tiles and ceramics | 17 01 02 · 17 01 03 | 40 t |
| Metals: iron and steel · mixed metals | 17 04 05 · 17 04 07 | 2 t |
| Wood | 17 02 01 | 1 t |
| Glass | 17 02 02 | 1 t |
| Plastic | 17 02 03 | 0.5 t |
| Paper and cardboard | 15 01 01 (packaging) | 0.5 t |
| Gypsum | 17 08 02 | No threshold in the decree. See Act 7/2022 |
| Mixed, non-hazardous | 17 09 04 | — |
Quantities are estimated from the project’s measurements: the cubic metres demolished, the areas of partitions or flooring removed, the packaging of what is installed. The decree sets no ratios per square metre. A tonnage that bears no relation to what the estimate demolishes is easy to spot.
Refurbishments: the hazardous waste inventory
In demolition, refurbishment, repair or alteration work, article 4.1.b also requires an inventory of the hazardous waste that will be produced. Its selective removal must be planned so it is not mixed with the rest. It must go to authorised hazardous waste managers. Act 7/2022 repeats the point in article 30.1: in demolitions, hazardous substances, asbestos in particular, are removed without mixing and handled safely.
In a building of some age it is common to find asbestos-cement downpipes, tanks or sheets (17 06 05*). Sometimes there is also insulation containing asbestos (17 06 01*). Asbestos work has its own safety rules, Royal Decree 396/2006. It is done by a specialist contractor. The study does not solve it: it must identify it. And the estimate must include its removal. A report that mentions asbestos cement while the estimate has no item for it is one of the easiest inconsistencies to see. The retail-to-residential change of use covers others.
What Act 7/2022 adds
The 2022 waste act does not amend the text of Royal Decree 105/2008: its consolidated version in the official gazette is still the original. What it does is add duties in its article 30:
- From 1 July 2022, non-hazardous construction and demolition waste is sorted at least into wood, minerals (concrete, bricks, tiles, ceramics and stone), metals, glass, plastic and gypsum, preferably on site. Reusable items such as roof tiles, sanitaryware or structural elements are kept apart too.
- From 1 January 2024, demolition is selective and compulsory, removing at least those streams. Where the work is not required to have a management study, it is done on the basis of a prior study identifying the quantity of each stream.
- Article 26 sets public authorities a target of 70% by weight of non-hazardous construction and demolition waste going to reuse, recycling or other recovery. It is a target for the waste management plans, not a figure each job must reach.
The act does not repeat the thresholds in article 5.5 of the decree. Before writing the separation section, it is worth checking in the region’s rules and the council bylaw how the act’s sorting duty combines with those thresholds.
The deposit and the final paperwork
Where the work needs a permit, article 4.1.d requires the producer to provide the deposit or equivalent financial guarantee set by the region’s legislation. Article 6.3 says how it is calculated: on the cost in the management study. The authority may raise that cost, with reasons, if it considers it undervalued. Amounts and the return procedure are set by each region and, often, by each council’s bylaw.
During the works, the contractor gives the client a management plan setting out how it will meet the study. Once approved by the site supervision team and accepted by the owner, it becomes a contract document (article 5.1). At the end, the producer must keep for five years the documents proving how the waste was managed (article 4.1.c). They are usually what the council asks for to return the deposit.
Before you submit it
A quick pass over the study and the documents it is checked against:
- Job name, site, client and stage match the report.
- Quantities are given in tonnes and cubic metres, with their European list code.
- Quantities bear a relation to the demolition and measurements in the estimate.
- In a refurbishment there is a hazardous waste inventory that matches the report and the estimate items.
- The separation section covers the streams in article 30.2 of Act 7/2022 and the thresholds in article 5.5.
- Waste management is a separate chapter of the estimate, with the same figure in the study and the summary.
- The rules cited are current: nothing from Act 10/1998 or Act 22/2011, both repealed.
- The council bylaw on the deposit and its return has been checked.
If the study comes from a template, the last check is the most useful: search the text for any figure left from the previous job.
Where Archelo helps
Archelo recognises the waste management study among the application’s documents and flags it when it is missing for the type of work. It cross-checks the figures the study shares with the report and the estimate and points out what does not match, with the document and page of each figure. If it is missing, it drafts it with the project’s data and estimates the quantities. It does not choose the waste manager or set the deposit, which depend on the job and the council. You can see how it works on AI for architects.