DB-SI in a dwelling refurbishment: what to justify and what not

In a refurbishment DB-SI neither applies in full nor stops applying. It reaches what the work alters, escape routes if occupancy changes and protection systems if what carries them is touched. Existing safety can never be made worse.

Refurbishment or maintenance?The first thing that decides which part of DB-SI must be justified.
In this article
  1. The short version
  2. First: maintenance, refurbishment or change of use
  3. DB-SI’s three rules for refurbishment
  4. What DB-SI does not ask inside the dwelling
  5. What does apply when the work touches it
  6. Change of use and listed buildings
  7. What to write in the report
  8. How Archelo handles it

The short version

This justification is sometimes dismissed with «not applicable». That can leave the reviewer with doubts, because in a refurbishment DB-SI applies in part. We follow the Basic Document SI (fire safety) in its version of 4 March 2025, the Ministry’s annotated edition of the same date and article 2 of Part I of the code. The rules are Spanish. The logic of proportionate upgrading will be familiar to anyone who has worked on existing buildings elsewhere.

First: maintenance, refurbishment or change of use

Annex III of Part I defines the interventions in existing buildings: extension, refurbishment and change of use. Refurbishment is any work on an existing building other than that carried out solely for its maintenance. Maintenance is the periodic work to prevent deterioration or the one-off repairs that keep the building in good order. The Ministry’s comment puts it plainly: maintenance work does not have to apply the building code.

The same comment gives a useful example: taking down suspended ceilings to repair the infill blocks of a floor and putting them back is maintenance and can be limited to its purpose. Changing the layout, rebuilding bathrooms and kitchen or renewing a dwelling’s services is refurbishment. For refurbishment, article 2.3 of Part I requires the code to be justified in a project or in a report signed by a qualified professional. Where the procedure is a declaration of compliance, the applicant must state that such a project or report exists.

DB-SI’s three rules for refurbishment

The introduction to DB-SI (section III) sets out how it applies to refurbishments that keep the use. There are three rules and the justification should go through them one by one:

RuleWhat it saysWhat it means for a dwelling
9. Altered elementsThe document applies to the elements the work alters, provided that brings them closer to it.Whatever is rebuilt is rebuilt to the document: a wall shared with another dwelling, a floor slab, a service penetration.
10. Escape and installationsIf occupancy or its distribution relative to the means of escape changes, the document reaches those too. If the supports of fire protection installations are affected, the installations are upgraded.An internal refurbishment seldom changes the building’s means of escape. Splitting one dwelling into two or joining two may.
11. No worseningThe work cannot reduce existing safety conditions where they fall short of the document.No unprotected opening in a wall that currently separates and no unsealed penetration that did not exist before.

The Ministry’s comment adds the key to reading them: no intervention is expected to bring the whole building up to the document, which «in many cases would be impossible». What is expected is proportion between the scope of the work and the safety improvement. Where the document cannot be met, article 2.3 of Part I allows the greatest possible degree of effective compliance. The project justifies it and the as-built documentation records the level reached.

What DB-SI does not ask inside the dwelling

Many of the requirements stop at the dwelling’s front door. It is worth saying so in the report with the clause, rather than a bare «not applicable»:

  • Escape routes. Annex SI A excludes points inside dwellings from the origin of evacuation. The route lengths in SI 3 table 3.1 are measured in the common areas, from each dwelling’s door.
  • Reaction to fire of linings. SI 1 table 4.1 asks for C-s2,d0 on walls and ceilings and EFL on floors in occupiable areas. Its note 4 excludes the inside of dwellings. The row for concealed spaces (suspended ceilings, raised floors) exempts those inside them.
  • Fire protection installations. For residential use, SI 4 table 1.1 asks for a dry riser above 24 m of evacuation height, detection and alarm above 50 m and hydrants from 5,000 m² of floor area. Extinguishers go within 15 m of every origin of evacuation, that is, in the common areas. An internal refurbishment does not trigger them.
  • Occupancy. The design density for dwelling floors is 20 m² per person (SI 3 table 2.1). It only matters if the work changes the number of dwellings or how they relate to the stair.

If the work reaches the stair or the entrance hall, those are common areas and all of the above applies.

What does apply when the work touches it

Where a dwelling refurbishment usually has something real to justify is at its edges: what separates it from other dwellings, from the common areas and from the building next door.

ElementRequirementClause
Walls and floors between dwellingsAt least EI 60SI 1, table 1.1
Service penetrations through themKeep their resistance with fire stopping or EI t through-elements. Penetrations up to 50 cm² are excludedSI 1, section 3
Continuity in concealed spacesCompartmentation carries on through shafts, cavities, suspended ceilings and raised floorsSI 1, section 3
Party wall with another buildingAt least EI 120SI 2, section 1
Structure being alteredFor residential buildings, R 60 above ground up to 15 m of evacuation height and R 120 in basements. For a single-family house, R 30SI 6, table 3.1
Façade systems, if the façade is rebuiltReaction to fire D-s3,d0 up to 10 m high, C-s3,d0 up to 18 m and B-s3,d0 above, where they cover more than 10% of the surfaceSI 2, section 1
Storage room over 50 m² in the buildingSpecial-risk room, low, medium or high depending on its areaSI 1, table 2.1

Two details that are easy to miss. In terraced or semi-detached houses, the elements of the shared structure must have the resistance required for residential buildings, not for a single-family house (note 2 to SI 6 table 3.1). And article 2.4 of Part I requires the project to state whether the work touches the existing structure or not. Everything else is read in the light of that sentence.

Change of use and listed buildings

If a shop becomes a dwelling, it is no longer a refurbishment that keeps the use. Rule 8 of the introduction applies the document to the part that changes and to the means of escape serving it up to a safe external space. There is one express exception: where an area of another use is turned into a dwelling inside an existing residential building, the document need not be applied to the common means of escape. We cover the rest of a change of use in retail to residential change of use.

In a listed building, where the document is incompatible with its protection grade, alternative solutions may be used that allow the greatest technical and economic degree of compliance. The as-built documentation must record any limits on use arising from the level reached (section III of the introduction). The alternative has to be described and justified: the listing explains why the document is not met but does not replace the justification.

What to write in the report

In a dwelling refurbishment, the DB-SI justification usually fits on half a page. What should be written down:

  • The type of intervention under annex III of Part I and whether it touches the structure (article 2.4).
  • The building’s use, evacuation height and whether the dwelling is a house or part of a block of flats.
  • Which elements the work alters and how they meet the document: EI 60 separations, EI 120 party wall, structure with its R.
  • Whether occupancy or its relation to the stair changes and why the building’s means of escape are unaffected.
  • Whether the supports of the building’s fire protection installations are affected and what is done about them.
  • How service penetrations through compartment elements are solved: sealant, intumescent collar or EI duct.
  • The statement that existing safety conditions are not reduced.
  • If the document is not met, the solution adopted, why it was adopted and the level of performance that remains.

Common mistakes

  • Writing «not applicable, as this is a refurbishment»: the document does apply, through rules 9, 10 and 11.
  • Asking for C-s2,d0 linings inside the dwelling or justifying escape routes within it.
  • Replacing a wall shared with another dwelling with a plasterboard system without stating its EI.
  • Running new extract ducts or soil stacks through floors without saying how the penetration is sealed.
  • A report saying the structure is untouched and drawings showing an opening in a load-bearing wall. We discuss cross-checking report, drawings and estimate in what a project report must contain.

How Archelo handles it

Archelo shows in its regulations view the DB-SI figures for the project’s use, each with its table: design occupancy, exits, route lengths and widths. It also checks whether the report justifies DB-SI and whether what it says matches the drawings and the estimate. It does not decide whether a job is maintenance or refurbishment, nor certify the fire resistance of a build-up: that is the designer’s judgement. What it points out is where it still needs writing down.

You can see how it works on AI for architects. This article is for information and does not replace checking the code’s text in force, the local bylaws or any heritage rules that apply to the building.

Keep reading

10 · 3 · 1The years of liability for structure, habitability and finishes, counted from handover.LOE, art. 17.1

The Building Act in a practice: who answers for what and from when

Each party answers for its own part for ten, three or one year depending on the defect. Every period runs from handover, so a badly closed handover record moves the clock and leaves parts uncovered.

Ground floor plus one, seven to twelve dwellings upstairsThe decree requires the lift installed. The building code settles for leaving room for one.

Accessibility in Andalusia: Decree 293/2009 in housing projects

In a residential building, Decree 293/2009 governs communal areas and reserved dwellings, not the inside of the others. It applies alongside DB-SUA. Where the two differ, the stricter one must be met.

Art. 299.2Other authorities’ approvals come before the permit. A permit cannot be conditional on obtaining them later.LISTA Regulations

How to organise a project application before you submit it

A well-organised application prevents a missing document, an invalid signature or two figures that disagree. The council’s own list is the one that counts. Documents are sorted by when they go in: with the application, before work starts or at completion. Before signing, the same figure has to read the same in every document.

Four jobs that must be certified
  • Execution project
  • Final certificate
  • Legalisation
  • Demolition without explosives

Visado: when certification by the professional body is mandatory

Certification by the professional body is voluntary except for a closed list of work. In building, the list includes the execution project and the final certificate. The basic design is not on it and a permit can be applied for with it.

AI for architects: can it check a project against building regulations?

Software can already verify much of what a project has to state, with the article and page of every figure. What it cannot do is decide what your project means. And nothing failing does not mean it complies.

€450,759.08The contract price, with VAT, from which the study must be the full one.RD 1627/1997, art. 4.1

The basic health and safety study (RD 1627/1997): when it is enough and what it contains

Every project-based job carries a health and safety study, full or basic. Four conditions decide which. The cost threshold is measured on the contract budget with VAT, not on the material execution budget.

Seven minimum contents
  • Estimate and prevention
  • Destination and separation
  • Drawings and specifications
  • Cost

The construction waste management study (RD 105/2008): what it must include

RD 105/2008 requires the waste management study and the designer writes it. It has seven minimum contents and five of them already go in the basic design. A refurbishment adds an inventory of hazardous waste.

1.50 mThe height that most often makes usable area differ from one document to another.

The usable and gross floor area schedule: the most common mistakes

The usable area in a valuation, the one on the energy certificate and the cadastre’s gross area are not measured the same way. Countable area is set by each municipality. That is why a schedule has to say which criterion it uses.

ChatGPT for architects: what it is good for, where it fails with regulations and how to check it

ChatGPT and the other general assistants draft, summarise and explain well. They are not a source of regulations: use them for the former and never accept a requirement without opening the official text.

Documents for a building permit application in Spain: the complete file, in order and reviewed

A permit application with a project brings together five groups of documents. Each council publishes its own list, though the core is common across Spain. Before submitting, the most useful check is that they all say the same.

Art. 138What goes by self-declaration in Andalusia. Everything else needs a permit.LISTA

Self-declaration or building permit in Andalusia: when each applies

In Andalusia the permit is the rule and the self-declaration the exception listed in article 138 of the LISTA. Needing a project does not mean needing a permit: a refurbishment with a project on urban land can go by self-declaration if it leaves occupancy, height, buildable area and number of dwellings unchanged.

DB-SUA in housing: stairs, guarding and changes of level

The stair in a duplex and the communal stair are not justified with the same figures. Their balustrades are: the conditions against climbing and openings are the same throughout the building.

50 l/sThe minimum extraction over the hob, with its own duct.CTE DB-HS 3

DB-HS 3: how to justify a dwelling’s ventilation rates

Table 2.1 gives the flows and the justification does not end there. Supply and extract must be balanced, openings and ducts sized and the kitchen solved. A two-bedroom flat shows how.

What a project report must contain under Spain’s building code and how to review it before submission

The report is where a project is justified. Spain’s building code sets its minimum content. What must be written depends on the work, the use, the stage and the council.

Is it allowed? Does it comply? Does the building permit it?The three questions of a shop-to-dwelling change, in order.

Retail to residential: what to check before applying for the permit

Changing a shop’s use is work that needs a project, however small it looks. The first question is not the building code but the plan: if housing is not allowed on that floor and that street, no project will do.

How to use AI in an architecture practice: from brief to permit

When people talk about AI for architects they almost always mean images. But a project is a long chain, from brief to permit. Each stage has work you can delegate and work you cannot.

40% · 20%The national minimum reserve: on rural land being urbanised, and on urbanised land under renewal.TRLSRU, art. 20.1.b

Affordable housing reserve: what to check before fixing the percentage

The national Land Act sets a minimum of 40% or 20% depending on the development. Regional law, the current plan and transitional provisions can change that figure on each site.

Pilot programme

Try Archelo on a real case.

Archelo helps you prepare all your project documents, analyses the drawings, tells you whether it complies before you submit and keeps everything organised. Want to try it?

Watch the demo

Request access

Try Archelo on your own projects. Fill in the form and we will email you as soon as your access is ready.

We use these details only to give you access.