The Building Act in a practice: who answers for what and from when
Each party answers for its own part for ten, three or one year depending on the defect. Every period runs from handover, so a badly closed handover record moves the clock and leaves parts uncovered.

In this article
- The short version
- First: whether your works fall under the act
- Who is who
- Three periods and one clock
- Handover: the document that starts the clock
- How it is shared and where it gets complicated
- The ten-year policy is not your policy
- What a practice should keep in writing
- Where Archelo helps
- Frequently asked questions
The short version
This guide draws on the consolidated text of the Building Act, Law 38/1999 (the LOE), Part I of the building code and Royal Decree 1627/1997.
First: whether your works fall under the act
Article 2.2 sets what counts as building work under the LOE and needs a project. That means new build, except minor single-storey constructions that are neither residential nor public. On an existing building it means total interventions and partial ones that essentially change the exterior composition, the volume or the structural system as a whole. Also those that change the characteristic uses. On protected buildings it means total works and partial ones that affect what is protected.
Refitting the inside of a flat without touching any of that falls outside the definition. The contract remains and it is worth taking legal advice on what else applies. A change of use from shop to dwelling deserves a careful look, as it depends on whether the building’s characteristic use changes. Whether works need a project is a separate question from whether they go by permit or self-declaration: that is decided by the applicable rules to which article 5 refers.
Who is who
Article 8 defines as parties everyone involved in the process, with the duties set by the act, other applicable rules and their contract. This is what gets looked up most for each:
| Party | Their part | Article |
|---|---|---|
| Developer (promotor) | Right to build, prior information, permits, handover record and insurance | 9 |
| Designer (proyectista) | Write the project in line with the rules and the contract. Agree partial collaborations with the developer | 10 |
| Contractor | Build to the project, appoint a site manager, sign the setting-out and handover records | 11 |
| Site director (director de obra) | Verify setting-out, foundations and structure, resolve contingencies, sign the final certificate and prepare the as-built documents | 12 |
| Works execution director | Verify receipt of products, order tests, direct material execution, sign the final certificate and valuations | 13 |
| Quality control, suppliers, owners and users | Technical assistance and results, product quality, upkeep and use according to the instructions | 14, 15 and 16 |
In residential use, the project and site direction fall to an architect and execution to a technical architect (articles 10.2.a, 12.3.a and 13.2.a). Article 12.3.g contemplates one person holding both directions. On a dwelling do not assume it: article 13.2.a asks there for a technical architect’s qualification. The health and safety coordinator is not in the chapter on parties. The developer appoints one when there are several designers or several firms or self-employed workers (Royal Decree 1627/1997, article 3). The qualifications are in the LOE’s fourth additional provision and the document in the guide to the health and safety study.
Three periods and one clock
Article 17.1 covers material damage to the building and liability runs to owners and later purchasers, without prejudice to contractual liability.
| Period | What it covers | Who | Reference guarantee (art. 19) |
|---|---|---|---|
| 10 years | Defects in foundations, columns, beams, floors, load-bearing walls or other structural elements that directly compromise strength and stability | The parties involved | Minimum cover of 100% |
| 3 years | Defects in building elements or services that breach the habitability of article 3.1.c: hygiene and health, noise, energy and other functional aspects | The parties involved | Minimum cover of 30% |
| 1 year | Workmanship defects in finishing elements | The contractor | Minimum cover of 5% or a 5% retention |
The three-year period refers only to letter c) of article 3, so fire safety and safety in use, which sit in letter b), are not on that list. The article itself preserves contractual liability.
The guarantee period and the time to claim are two different things. The damage must appear within the period and, from when it occurs, there are two years to bring the action (article 18.1). An example: with handover on 15 March 2027, structural damage arising in February 2036 falls within the ten years and can be claimed until February 2038.
Handover: the document that starts the clock
Article 6 asks for a record signed at least by developer and contractor, with the final cost of material execution, the declaration with or without reservations and the final certificate attached. Unless agreed otherwise, handover takes place within thirty days of completion. If they pass with no written reservations or rejection, it is deemed to have happened tacitly.
That is where reservations matter. Article 17.1 counts the periods from handover without reservations or from their remedy, while article 6.5 counts them from signing the record or tacit handover. And article 19.9.i excludes from the guarantees, unless agreed otherwise, claims on parts with reservations until the remedy is recorded in a new record signed by those who signed the handover. So reservations are written objectively and with a deadline (6.2.d). Once fixed, the separate record gets signed, even if the building is already occupied.
How it is shared and where it gets complicated
The rule is that liability is personal and individual, for your own acts and for those you must answer for (17.2). The exception comes up often: if the cause cannot be attributed or there is shared fault with no defined degree, liability is joint and several (17.3). The developer is always jointly liable with the others towards purchasers for construction defects. What affects a practice most:
- Outside calculations. Whoever commissions calculations, studies, opinions or reports from another professional is directly liable if they are inadequate or wrong. They can then claim back from the author (17.5). That differs from a specialist who signs their own work (10.2.a) or from a partial project, whose ownership each designer assumes (10.1).
- A project contracted to two. If it is contracted jointly with more than one designer, they are jointly and severally liable (17.5). The same goes for site direction contracted to more than one professional (17.7).
- Someone else’s project. Whoever agrees to direct works they did not design takes on the project’s omissions, deficiencies or imperfections, with recourse against the designer (17.7). Before accepting, read it as if you were about to sign it.
- Final certificate. Those who sign it answer for its truth and accuracy (17.7).
- In a lawsuit. The defendant can ask, within the time to respond, for the claim to be served on other parties. If they do not appear, the judgment can be enforced against them (seventh additional provision).
Where the practice is a company, the act requires it to appoint the qualified professional. Whether the company, the professional or both answer is something these articles do not settle alone: ask your adviser and your insurer.
The ten-year policy is not your policy
The second additional provision makes only the ten-year guarantee mandatory and only for buildings mainly intended as housing. The one and three-year guarantees become mandatory if a royal decree so provides. The ten-year one is not required of an individual self-developer of a single house for their own use, unless they sell within the period and the buyer does not release them. Nor in the rehabilitation of mainly residential buildings whose new-build permit was applied for before the act came into force on 6 May 2000.
It is worth being clear whose policy it is. In the ten-year material damage insurance, the policyholder is the developer and the insured are the developer and later purchasers (19.2.a). The professional does not appear as insured and article 18.2 recognises the insurers’ right of recourse against the parties. Without proof of this guarantee, the new-build deed is neither authorised nor registered (article 20). Unless agreed otherwise, it does not cover damage to neighbouring properties, personal injury or damage from misuse or works after handover (19.9). Your own professional policy is a separate matter that these articles do not regulate: review it with your broker.
What a practice should keep in writing
The act does not give this as a list. Each point answers one of its articles:
- In the report, the parties section: developer, designer and other professionals (Part I of the code, annex I, 1.1). The guide to the report’s content places it in context.
- In the appointment, which collaborations are agreed with the developer and who signs each part: what is a partial project, what is specialist work and what is a calculation you commission.
- For each outside calculation, the document signed by its author and the contract. That is what allows a later claim back.
- Before accepting site direction, any objections to the other designer’s project in writing.
- Each change on site, with the developer’s agreement (LOE 9.2.b and 12.3.d, Part I 7.1) and the instructions in the site order book.
- Each alternative to a basic document, with the developer’s agreement and its documentary justification (Part I, 5.1.3.b).
- The full handover record and, if there were reservations, the separate record of their remedy.
- The building logbook: project with changes, record, list of parties and instructions for use and maintenance (LOE, article 7), with the maintenance plan (Part I, 8.1).
What the council asks for in the application is a different list, set out in the guide to building permit documents.
Where Archelo helps
Archelo helps you draft the report with its parties section and flags what is still missing to identify the developer. When reviewing the application it checks that the section is in the report. It also helps you prepare the health and safety study with the professionals the report already names. More on AI for architects.
Frequently asked questions
How long is an architect liable for a building under the Spanish Building Act?
Ten years for damage from defects that affect the structure and compromise strength and stability. Three years for defects that breach the habitability requirements. The one year for finishes falls on the contractor alone (LOE, article 17.1).
When do the liability periods start?
From handover without reservations or from the moment the reservations are remedied (article 17.1). If the developer raises no written reservations or rejection within thirty days, handover is deemed to have happened tacitly (article 6.4).
How long is there to claim for damage?
Two years from when the damage occurs, provided it appeared within the ten, three or one-year period (LOE, article 18.1). Actions for breach of contract are separate.
Who is liable if another professional did the structural calculation?
The designer who commissioned it is directly liable for damage arising from its inadequacy, error or inaccuracy. They can then claim back from the author (LOE, article 17.5).
What does a site director take on with someone else’s project?
The liability arising from the project’s omissions, deficiencies or imperfections, with recourse against the designer (LOE, article 17.7).
















