The Building Act in a practice: who answers for what and from when

Each party answers for its own part for ten, three or one year depending on the defect. Every period runs from handover, so a badly closed handover record moves the clock and leaves parts uncovered.

10 · 3 · 1The years of liability for structure, habitability and finishes, counted from handover.LOE, art. 17.1
In this article
  1. The short version
  2. First: whether your works fall under the act
  3. Who is who
  4. Three periods and one clock
  5. Handover: the document that starts the clock
  6. How it is shared and where it gets complicated
  7. The ten-year policy is not your policy
  8. What a practice should keep in writing
  9. Where Archelo helps
  10. Frequently asked questions

The short version

This guide draws on the consolidated text of the Building Act, Law 38/1999 (the LOE), Part I of the building code and Royal Decree 1627/1997.

First: whether your works fall under the act

Article 2.2 sets what counts as building work under the LOE and needs a project. That means new build, except minor single-storey constructions that are neither residential nor public. On an existing building it means total interventions and partial ones that essentially change the exterior composition, the volume or the structural system as a whole. Also those that change the characteristic uses. On protected buildings it means total works and partial ones that affect what is protected.

Refitting the inside of a flat without touching any of that falls outside the definition. The contract remains and it is worth taking legal advice on what else applies. A change of use from shop to dwelling deserves a careful look, as it depends on whether the building’s characteristic use changes. Whether works need a project is a separate question from whether they go by permit or self-declaration: that is decided by the applicable rules to which article 5 refers.

Who is who

Article 8 defines as parties everyone involved in the process, with the duties set by the act, other applicable rules and their contract. This is what gets looked up most for each:

PartyTheir partArticle
Developer (promotor)Right to build, prior information, permits, handover record and insurance9
Designer (proyectista)Write the project in line with the rules and the contract. Agree partial collaborations with the developer10
ContractorBuild to the project, appoint a site manager, sign the setting-out and handover records11
Site director (director de obra)Verify setting-out, foundations and structure, resolve contingencies, sign the final certificate and prepare the as-built documents12
Works execution directorVerify receipt of products, order tests, direct material execution, sign the final certificate and valuations13
Quality control, suppliers, owners and usersTechnical assistance and results, product quality, upkeep and use according to the instructions14, 15 and 16

In residential use, the project and site direction fall to an architect and execution to a technical architect (articles 10.2.a, 12.3.a and 13.2.a). Article 12.3.g contemplates one person holding both directions. On a dwelling do not assume it: article 13.2.a asks there for a technical architect’s qualification. The health and safety coordinator is not in the chapter on parties. The developer appoints one when there are several designers or several firms or self-employed workers (Royal Decree 1627/1997, article 3). The qualifications are in the LOE’s fourth additional provision and the document in the guide to the health and safety study.

Three periods and one clock

Article 17.1 covers material damage to the building and liability runs to owners and later purchasers, without prejudice to contractual liability.

PeriodWhat it coversWhoReference guarantee (art. 19)
10 yearsDefects in foundations, columns, beams, floors, load-bearing walls or other structural elements that directly compromise strength and stabilityThe parties involvedMinimum cover of 100%
3 yearsDefects in building elements or services that breach the habitability of article 3.1.c: hygiene and health, noise, energy and other functional aspectsThe parties involvedMinimum cover of 30%
1 yearWorkmanship defects in finishing elementsThe contractorMinimum cover of 5% or a 5% retention

The three-year period refers only to letter c) of article 3, so fire safety and safety in use, which sit in letter b), are not on that list. The article itself preserves contractual liability.

The guarantee period and the time to claim are two different things. The damage must appear within the period and, from when it occurs, there are two years to bring the action (article 18.1). An example: with handover on 15 March 2027, structural damage arising in February 2036 falls within the ten years and can be claimed until February 2038.

Handover: the document that starts the clock

Article 6 asks for a record signed at least by developer and contractor, with the final cost of material execution, the declaration with or without reservations and the final certificate attached. Unless agreed otherwise, handover takes place within thirty days of completion. If they pass with no written reservations or rejection, it is deemed to have happened tacitly.

That is where reservations matter. Article 17.1 counts the periods from handover without reservations or from their remedy, while article 6.5 counts them from signing the record or tacit handover. And article 19.9.i excludes from the guarantees, unless agreed otherwise, claims on parts with reservations until the remedy is recorded in a new record signed by those who signed the handover. So reservations are written objectively and with a deadline (6.2.d). Once fixed, the separate record gets signed, even if the building is already occupied.

How it is shared and where it gets complicated

The rule is that liability is personal and individual, for your own acts and for those you must answer for (17.2). The exception comes up often: if the cause cannot be attributed or there is shared fault with no defined degree, liability is joint and several (17.3). The developer is always jointly liable with the others towards purchasers for construction defects. What affects a practice most:

  • Outside calculations. Whoever commissions calculations, studies, opinions or reports from another professional is directly liable if they are inadequate or wrong. They can then claim back from the author (17.5). That differs from a specialist who signs their own work (10.2.a) or from a partial project, whose ownership each designer assumes (10.1).
  • A project contracted to two. If it is contracted jointly with more than one designer, they are jointly and severally liable (17.5). The same goes for site direction contracted to more than one professional (17.7).
  • Someone else’s project. Whoever agrees to direct works they did not design takes on the project’s omissions, deficiencies or imperfections, with recourse against the designer (17.7). Before accepting, read it as if you were about to sign it.
  • Final certificate. Those who sign it answer for its truth and accuracy (17.7).
  • In a lawsuit. The defendant can ask, within the time to respond, for the claim to be served on other parties. If they do not appear, the judgment can be enforced against them (seventh additional provision).

Where the practice is a company, the act requires it to appoint the qualified professional. Whether the company, the professional or both answer is something these articles do not settle alone: ask your adviser and your insurer.

The ten-year policy is not your policy

The second additional provision makes only the ten-year guarantee mandatory and only for buildings mainly intended as housing. The one and three-year guarantees become mandatory if a royal decree so provides. The ten-year one is not required of an individual self-developer of a single house for their own use, unless they sell within the period and the buyer does not release them. Nor in the rehabilitation of mainly residential buildings whose new-build permit was applied for before the act came into force on 6 May 2000.

It is worth being clear whose policy it is. In the ten-year material damage insurance, the policyholder is the developer and the insured are the developer and later purchasers (19.2.a). The professional does not appear as insured and article 18.2 recognises the insurers’ right of recourse against the parties. Without proof of this guarantee, the new-build deed is neither authorised nor registered (article 20). Unless agreed otherwise, it does not cover damage to neighbouring properties, personal injury or damage from misuse or works after handover (19.9). Your own professional policy is a separate matter that these articles do not regulate: review it with your broker.

What a practice should keep in writing

The act does not give this as a list. Each point answers one of its articles:

  • In the report, the parties section: developer, designer and other professionals (Part I of the code, annex I, 1.1). The guide to the report’s content places it in context.
  • In the appointment, which collaborations are agreed with the developer and who signs each part: what is a partial project, what is specialist work and what is a calculation you commission.
  • For each outside calculation, the document signed by its author and the contract. That is what allows a later claim back.
  • Before accepting site direction, any objections to the other designer’s project in writing.
  • Each change on site, with the developer’s agreement (LOE 9.2.b and 12.3.d, Part I 7.1) and the instructions in the site order book.
  • Each alternative to a basic document, with the developer’s agreement and its documentary justification (Part I, 5.1.3.b).
  • The full handover record and, if there were reservations, the separate record of their remedy.
  • The building logbook: project with changes, record, list of parties and instructions for use and maintenance (LOE, article 7), with the maintenance plan (Part I, 8.1).

What the council asks for in the application is a different list, set out in the guide to building permit documents.

Where Archelo helps

Archelo helps you draft the report with its parties section and flags what is still missing to identify the developer. When reviewing the application it checks that the section is in the report. It also helps you prepare the health and safety study with the professionals the report already names. More on AI for architects.

Frequently asked questions

How long is an architect liable for a building under the Spanish Building Act?

Ten years for damage from defects that affect the structure and compromise strength and stability. Three years for defects that breach the habitability requirements. The one year for finishes falls on the contractor alone (LOE, article 17.1).

When do the liability periods start?

From handover without reservations or from the moment the reservations are remedied (article 17.1). If the developer raises no written reservations or rejection within thirty days, handover is deemed to have happened tacitly (article 6.4).

How long is there to claim for damage?

Two years from when the damage occurs, provided it appeared within the ten, three or one-year period (LOE, article 18.1). Actions for breach of contract are separate.

Who is liable if another professional did the structural calculation?

The designer who commissioned it is directly liable for damage arising from its inadequacy, error or inaccuracy. They can then claim back from the author (LOE, article 17.5).

What does a site director take on with someone else’s project?

The liability arising from the project’s omissions, deficiencies or imperfections, with recourse against the designer (LOE, article 17.7).

Keep reading

Ground floor plus one, seven to twelve dwellings upstairsThe decree requires the lift installed. The building code settles for leaving room for one.

Accessibility in Andalusia: Decree 293/2009 in housing projects

In a residential building, Decree 293/2009 governs communal areas and reserved dwellings, not the inside of the others. It applies alongside DB-SUA. Where the two differ, the stricter one must be met.

Art. 299.2Other authorities’ approvals come before the permit. A permit cannot be conditional on obtaining them later.LISTA Regulations

How to organise a project application before you submit it

A well-organised application prevents a missing document, an invalid signature or two figures that disagree. The council’s own list is the one that counts. Documents are sorted by when they go in: with the application, before work starts or at completion. Before signing, the same figure has to read the same in every document.

Four jobs that must be certified
  • Execution project
  • Final certificate
  • Legalisation
  • Demolition without explosives

Visado: when certification by the professional body is mandatory

Certification by the professional body is voluntary except for a closed list of work. In building, the list includes the execution project and the final certificate. The basic design is not on it and a permit can be applied for with it.

AI for architects: can it check a project against building regulations?

Software can already verify much of what a project has to state, with the article and page of every figure. What it cannot do is decide what your project means. And nothing failing does not mean it complies.

€450,759.08The contract price, with VAT, from which the study must be the full one.RD 1627/1997, art. 4.1

The basic health and safety study (RD 1627/1997): when it is enough and what it contains

Every project-based job carries a health and safety study, full or basic. Four conditions decide which. The cost threshold is measured on the contract budget with VAT, not on the material execution budget.

Seven minimum contents
  • Estimate and prevention
  • Destination and separation
  • Drawings and specifications
  • Cost

The construction waste management study (RD 105/2008): what it must include

RD 105/2008 requires the waste management study and the designer writes it. It has seven minimum contents and five of them already go in the basic design. A refurbishment adds an inventory of hazardous waste.

1.50 mThe height that most often makes usable area differ from one document to another.

The usable and gross floor area schedule: the most common mistakes

The usable area in a valuation, the one on the energy certificate and the cadastre’s gross area are not measured the same way. Countable area is set by each municipality. That is why a schedule has to say which criterion it uses.

ChatGPT for architects: what it is good for, where it fails with regulations and how to check it

ChatGPT and the other general assistants draft, summarise and explain well. They are not a source of regulations: use them for the former and never accept a requirement without opening the official text.

Documents for a building permit application in Spain: the complete file, in order and reviewed

A permit application with a project brings together five groups of documents. Each council publishes its own list, though the core is common across Spain. Before submitting, the most useful check is that they all say the same.

Art. 138What goes by self-declaration in Andalusia. Everything else needs a permit.LISTA

Self-declaration or building permit in Andalusia: when each applies

In Andalusia the permit is the rule and the self-declaration the exception listed in article 138 of the LISTA. Needing a project does not mean needing a permit: a refurbishment with a project on urban land can go by self-declaration if it leaves occupancy, height, buildable area and number of dwellings unchanged.

DB-SUA in housing: stairs, guarding and changes of level

The stair in a duplex and the communal stair are not justified with the same figures. Their balustrades are: the conditions against climbing and openings are the same throughout the building.

Refurbishment or maintenance?The first thing that decides which part of DB-SI must be justified.

DB-SI in a dwelling refurbishment: what to justify and what not

In a refurbishment DB-SI neither applies in full nor stops applying. It reaches what the work alters, escape routes if occupancy changes and protection systems if what carries them is touched. Existing safety can never be made worse.

50 l/sThe minimum extraction over the hob, with its own duct.CTE DB-HS 3

DB-HS 3: how to justify a dwelling’s ventilation rates

Table 2.1 gives the flows and the justification does not end there. Supply and extract must be balanced, openings and ducts sized and the kitchen solved. A two-bedroom flat shows how.

What a project report must contain under Spain’s building code and how to review it before submission

The report is where a project is justified. Spain’s building code sets its minimum content. What must be written depends on the work, the use, the stage and the council.

Is it allowed? Does it comply? Does the building permit it?The three questions of a shop-to-dwelling change, in order.

Retail to residential: what to check before applying for the permit

Changing a shop’s use is work that needs a project, however small it looks. The first question is not the building code but the plan: if housing is not allowed on that floor and that street, no project will do.

How to use AI in an architecture practice: from brief to permit

When people talk about AI for architects they almost always mean images. But a project is a long chain, from brief to permit. Each stage has work you can delegate and work you cannot.

40% · 20%The national minimum reserve: on rural land being urbanised, and on urbanised land under renewal.TRLSRU, art. 20.1.b

Affordable housing reserve: what to check before fixing the percentage

The national Land Act sets a minimum of 40% or 20% depending on the development. Regional law, the current plan and transitional provisions can change that figure on each site.

Pilot programme

Try Archelo on a real case.

Archelo helps you prepare all your project documents, analyses the drawings, tells you whether it complies before you submit and keeps everything organised. Want to try it?

Watch the demo

Request access

Try Archelo on your own projects. Fill in the form and we will email you as soon as your access is ready.

We use these details only to give you access.