DB-HS 3: how to justify a dwelling’s ventilation rates

Table 2.1 gives the flows and the justification does not end there. Supply and extract must be balanced, openings and ducts sized and the kitchen solved. A two-bedroom flat shows how.

50 l/sThe minimum extraction over the hob, with its own duct.CTE DB-HS 3
In this article
  1. The short version
  2. What it applies to
  3. The requirement and table 2.1
  4. A worked example: a two-bedroom flat
  5. From flows to openings and ducts
  6. The kitchen and supplementary natural ventilation
  7. What to write in the report
  8. How Archelo handles it

The short version

This justification is sometimes settled with a generic sentence in the report. A council officer can ask to see it in figures. We follow the consolidated text of the Basic Document HS (version of 14 June 2022) and the Ministry’s annotated edition. The rules are Spanish. The reasoning will be familiar to anyone who has sized a whole-house extract system.

What it applies to

In residential buildings, section HS 3 applies to the inside of each dwelling, to refuse stores, storage rooms and car parks. In buildings of any other use, it applies only to car parks and garages (section 1.1). The Ministry’s comment makes clear it covers dwellings of every type, detached, semi-detached or terraced. For any other premises — an office, a shop, a hotel — the requirement is met by following the thermal installations regulation (RITE).

In a refurbishment or change of use the general rule in Part I of the code applies (article 2.3): the code applies to the work and is justified in the project or the report. Where full compliance is not feasible, the aim is the greatest possible degree of effective compliance and the project justifies it. Existing conditions are never made worse. When a shop becomes a home, ventilation is usually the hardest point. We cover it in retail to residential change of use.

The requirement and table 2.1

Section 2 states the requirement in terms of air quality. In each habitable room, the annual mean CO2 concentration must stay below 900 ppm and the annual accumulation above 1,600 ppm below 500,000 ppm·h, under the design conditions of appendix C. Each habitable room also gets a minimum of 1.5 l/s when unoccupied. Both are deemed met by constant-rate ventilation at the flows of table 2.1:

DwellingMain bedroomOther bedroomsLiving and diningWet rooms: total minimumWet rooms: minimum each
0 or 1 bedroom8 l/s—6 l/s12 l/s6 l/s
2 bedrooms8 l/s4 l/s8 l/s24 l/s7 l/s
3 or more bedrooms8 l/s4 l/s10 l/s33 l/s8 l/s

The table carries three notes. A dry room with several uses takes the flow of the most demanding one. If one room has a dry and a wet zone — the living room with an open kitchen — each zone gets its own flow. And a study or playroom counts as living space. Two rooms joined by a clear opening count as one room when the opening is at least 1.5 m² and one twentieth of their combined floor area (appendix A).

The alternative to the table is to justify the CO2 limits directly under appendix C (occupants, occupancy schedule, CO2 generation, doors closed). It is the route for demand-controlled systems and it needs a calculation attached to the project.

A worked example: a two-bedroom flat

An illustrative case, not a real project: a two-bedroom flat with a living-dining room, a separate kitchen, a bathroom and a toilet. Supply from the table adds up to 8 + 4 + 8 = 20 l/s. On the extract side, three wet rooms at 7 l/s give 21 l/s. That is below the 24 l/s total minimum, so extract is 24 l/s. A dwelling has a single airflow. The Ministry’s comment says how to close the gap: take the larger total and raise the flows on the other side, for instance in proportion, never below the table.

RoomTable 2.1BalancedOpening (table 4.1)
Main bedroom8 l/s supply9.6 l/sSupply 4 × 9.6 = 38.4 cm². Transfer 8 × 9.6 = 76.8 cm²
Bedroom 24 l/s supply4.8 l/sSupply 19.2 cm². Transfer 70 cm² (8 × 4.8 = 38.4 falls short of the minimum)
Living-dining room8 l/s supply9.6 l/sSupply 38.4 cm². Transfer 76.8 cm²
Kitchen, bathroom and toilet7 l/s each, 24 l/s total8 l/s eachExtract 4 × 8 = 32 cm² in each. Incoming transfer 70 cm²
Dwelling total20 l/s against 24 l/s24 l/sShared mechanical duct next to habitable rooms: 2.5 × 24 = 60 cm²

The areas are effective areas: the unobstructed section perpendicular to the airflow, not the grille’s nominal size. And sharing the extract between the three wet rooms is an airflow assumption that has to be written down, because the transfer openings depend on it.

From flows to openings and ducts

The dwelling needs a general hybrid or mechanical system (section 3.1.1). What to check on the drawings and in the report:

  • Supply in bedrooms, living and dining rooms, through trickle vents or fixed openings in the window frame of class 1 or higher under UNE-EN 12207:2017. Vents go more than 1.80 m above the floor. If the external joinery is class 1, its opening joints can count as supply. In hybrid systems, supply opens directly to the outside.
  • Transfer through the partitions between supply and extract rooms: a vent or the gap under the door will do, as long as it gives the table 4.1 area (at least 70 cm² or 8·qvp).
  • Extract in kitchen, bathrooms and toilets, less than 200 mm below the ceiling and more than 100 mm from any corner, connected to a duct. In a subdivided room, it goes in the zone with the WC or the hob.
  • Ducts: toilets, bathrooms, kitchens and storage rooms may share one. In mechanical systems, each section is at least 2.5·qvt cm² when next to a habitable room and 1.5·qvt on the roof. In hybrid systems, ducts are vertical and sized from table 4.2 by draught class and thermal zone. If shared, they serve no more than six storeys.
  • Discharge on the roof, at least 3 m from intakes, windows, doors and terraces. For hybrid systems, it also sits at least 1 m above the roof and above nearby obstacles.
  • All fans in the dwelling running together or another way of preventing reverse flow (section 3.2.5).

The kitchen and supplementary natural ventilation

The kitchen’s general extract is not enough. The cooking zone needs a system extracting at least 50 l/s, independent of the general ventilation (section 2.4). That means an extractor with a grease filter that signals when it needs cleaning, on its own duct. That duct cannot serve rooms of another use. If several extractors share a duct, each needs a non-return valve (sections 3.1.1.3 and 3.2.5).

Kitchens, dining rooms, bedrooms and living rooms also need supplementary natural ventilation: an opening external window or door (section 3.1.1.2) whose opening area is at least one twentieth of the room’s floor area (section 4.4). If it gives onto a courtyard and no planning rule sets the courtyard’s size, its plan must fit a circle whose diameter is one third of the lowest enclosing wall’s height and never less than 3 m (section 3.2.1). In deep premises with a single frontage, this is usually where the trouble lies.

What to write in the report

The justification fits on one page if it has the figures. What should be written down:

  • Dwelling type by number of bedrooms and the list of dry and wet rooms, with zones where uses mix.
  • Table 2.1 flows per room, with supply and extract totals and the dwelling’s balanced flow.
  • The airflow assumption: where air enters, which doors it crosses, where it leaves.
  • Effective area of each supply, transfer and extract opening, with the element that provides it (trickle vent, micro-ventilation, door gap).
  • System (hybrid or mechanical), route and section of each duct, discharge position and clearances.
  • Kitchen extractor at 50 l/s, its duct and its filter.
  • Opening window area against one twentieth of each room’s floor area.
  • In the specification, product acceptance (section 5.2) and installation conditions. In the user instructions, the table 7.1 maintenance.

Common mistakes

  • Copying the table without balancing: supply and extract with different totals.
  • Taking each wet room at its per-room minimum and missing the total minimum.
  • Drawing doors with no undercut or transfer vent at all or with less than 70 cm² of opening.
  • Serving the kitchen’s general extract and its hood from a single duct.
  • A report describing mechanical ventilation and an estimate with no vents, ducts or extractor. We discuss cross-checking them in what a project report must contain.

How Archelo handles it

On a dwelling’s project, Archelo works out the table 2.1 flows and the design flow from the area schedule. It checks whether the report justifies HS 3 with flows and whether the ventilation system and the kitchen extractor appear in both the report and the estimate. It also checks on the drawing whether the rooms that need one have an external opening. Each finding cites the section and the document page. It does not size openings or ducts: that stays with the designer.

You can see how it works on AI for architects. This article is for information and does not replace checking the code’s text in force or the local bylaws on courtyards and ventilation.

Keep reading

10 · 3 · 1The years of liability for structure, habitability and finishes, counted from handover.LOE, art. 17.1

The Building Act in a practice: who answers for what and from when

Each party answers for its own part for ten, three or one year depending on the defect. Every period runs from handover, so a badly closed handover record moves the clock and leaves parts uncovered.

Ground floor plus one, seven to twelve dwellings upstairsThe decree requires the lift installed. The building code settles for leaving room for one.

Accessibility in Andalusia: Decree 293/2009 in housing projects

In a residential building, Decree 293/2009 governs communal areas and reserved dwellings, not the inside of the others. It applies alongside DB-SUA. Where the two differ, the stricter one must be met.

Art. 299.2Other authorities’ approvals come before the permit. A permit cannot be conditional on obtaining them later.LISTA Regulations

How to organise a project application before you submit it

A well-organised application prevents a missing document, an invalid signature or two figures that disagree. The council’s own list is the one that counts. Documents are sorted by when they go in: with the application, before work starts or at completion. Before signing, the same figure has to read the same in every document.

Four jobs that must be certified
  • Execution project
  • Final certificate
  • Legalisation
  • Demolition without explosives

Visado: when certification by the professional body is mandatory

Certification by the professional body is voluntary except for a closed list of work. In building, the list includes the execution project and the final certificate. The basic design is not on it and a permit can be applied for with it.

AI for architects: can it check a project against building regulations?

Software can already verify much of what a project has to state, with the article and page of every figure. What it cannot do is decide what your project means. And nothing failing does not mean it complies.

€450,759.08The contract price, with VAT, from which the study must be the full one.RD 1627/1997, art. 4.1

The basic health and safety study (RD 1627/1997): when it is enough and what it contains

Every project-based job carries a health and safety study, full or basic. Four conditions decide which. The cost threshold is measured on the contract budget with VAT, not on the material execution budget.

Seven minimum contents
  • Estimate and prevention
  • Destination and separation
  • Drawings and specifications
  • Cost

The construction waste management study (RD 105/2008): what it must include

RD 105/2008 requires the waste management study and the designer writes it. It has seven minimum contents and five of them already go in the basic design. A refurbishment adds an inventory of hazardous waste.

1.50 mThe height that most often makes usable area differ from one document to another.

The usable and gross floor area schedule: the most common mistakes

The usable area in a valuation, the one on the energy certificate and the cadastre’s gross area are not measured the same way. Countable area is set by each municipality. That is why a schedule has to say which criterion it uses.

ChatGPT for architects: what it is good for, where it fails with regulations and how to check it

ChatGPT and the other general assistants draft, summarise and explain well. They are not a source of regulations: use them for the former and never accept a requirement without opening the official text.

Documents for a building permit application in Spain: the complete file, in order and reviewed

A permit application with a project brings together five groups of documents. Each council publishes its own list, though the core is common across Spain. Before submitting, the most useful check is that they all say the same.

Art. 138What goes by self-declaration in Andalusia. Everything else needs a permit.LISTA

Self-declaration or building permit in Andalusia: when each applies

In Andalusia the permit is the rule and the self-declaration the exception listed in article 138 of the LISTA. Needing a project does not mean needing a permit: a refurbishment with a project on urban land can go by self-declaration if it leaves occupancy, height, buildable area and number of dwellings unchanged.

DB-SUA in housing: stairs, guarding and changes of level

The stair in a duplex and the communal stair are not justified with the same figures. Their balustrades are: the conditions against climbing and openings are the same throughout the building.

Refurbishment or maintenance?The first thing that decides which part of DB-SI must be justified.

DB-SI in a dwelling refurbishment: what to justify and what not

In a refurbishment DB-SI neither applies in full nor stops applying. It reaches what the work alters, escape routes if occupancy changes and protection systems if what carries them is touched. Existing safety can never be made worse.

What a project report must contain under Spain’s building code and how to review it before submission

The report is where a project is justified. Spain’s building code sets its minimum content. What must be written depends on the work, the use, the stage and the council.

Is it allowed? Does it comply? Does the building permit it?The three questions of a shop-to-dwelling change, in order.

Retail to residential: what to check before applying for the permit

Changing a shop’s use is work that needs a project, however small it looks. The first question is not the building code but the plan: if housing is not allowed on that floor and that street, no project will do.

How to use AI in an architecture practice: from brief to permit

When people talk about AI for architects they almost always mean images. But a project is a long chain, from brief to permit. Each stage has work you can delegate and work you cannot.

40% · 20%The national minimum reserve: on rural land being urbanised, and on urbanised land under renewal.TRLSRU, art. 20.1.b

Affordable housing reserve: what to check before fixing the percentage

The national Land Act sets a minimum of 40% or 20% depending on the development. Regional law, the current plan and transitional provisions can change that figure on each site.

Pilot programme

Try Archelo on a real case.

Archelo helps you prepare all your project documents, analyses the drawings, tells you whether it complies before you submit and keeps everything organised. Want to try it?

Watch the demo

Request access

Try Archelo on your own projects. Fill in the form and we will email you as soon as your access is ready.

We use these details only to give you access.