Self-declaration or building permit in Andalusia: when each applies

In Andalusia the permit is the rule and the self-declaration the exception listed in article 138 of the LISTA. Needing a project does not mean needing a permit: a refurbishment with a project on urban land can go by self-declaration if it leaves occupancy, height, buildable area and number of dwellings unchanged.

Art. 138What goes by self-declaration in Andalusia. Everything else needs a permit.LISTA
In this article
  1. The short version
  2. The rule and the exception
  3. What goes by self-declaration
  4. Needing a project is not needing a permit
  5. Common cases
  6. Timelines and effects of each route
  7. The risk in a self-declaration
  8. Before choosing the route
  9. How Archelo handles it

The short version

Picking the wrong route costs months. A self-declaration that did not apply loses its effect and the process starts again. A permit sought for something that could simply be declared drags out the timeline for nothing. We follow the consolidated text of Andalusia’s Act 7/2021 on territorial sustainability (LISTA) in the Spanish Official Gazette, including the 2024 amendments by Decree-law 3/2024. We also follow the LISTA General Regulations (Decree 550/2022) as published in the regional gazette on 2 December 2022. The rules are Andalusian. Other Spanish regions draw the line elsewhere.

The rule and the exception

Article 137 requires a prior permit for works, construction, buildings, installations and land uses. It leaves out, among others, the acts subject to self-declaration or prior notice under article 138. The regulations say it even more plainly: article 291 requires a permit for new build, extensions, alterations or refurbishments «not subject to self-declaration».

In practice, that changes the question. The point is not whether the works are «minor» or «major». It is whether they fit one of article 138’s cases with every one of its conditions. If one fails, a permit is needed.

What goes by self-declaration

These are the article 138.1 cases that come up most in an architecture practice, with the conditions that must all be met:

CaseConditionsArticle
Small, technically simple worksNeeding no project under current law. The local bylaw may exempt from declaration those with no bearing on planning or building rulesLISTA 138.1 a)
Works on existing buildingsBuilding in line with the plan or lawfully non-conforming, on urban land not under a transformation scheme, with no change to footprint or height and no increase in floor area or number of dwellingsLISTA 138.1 b)
Change of useSame building and land conditions, no increase in dwellings and a use the plan allowsLISTA 138.1 f)
Occupation after the worksWorks finished and matching the permit or declaration, with a use in line with the rulesLISTA 138.1 d)
Occupation of existing buildings without worksOn urban land not under transformation, in line with the plan or lawfully non-conformingLISTA 138.1 e)
DemolitionThe building is not protected nor within the setting or area of a protected assetLISTA 138.1 g), added in 2024

The regulations add further cases in article 293.1. They include renewable self-consumption installations up to 100 kW and charging points in buildings on urban land (except in listed heritage assets). They also include preliminary work such as trial pits, boreholes and tests, plus changes during works under a permit that do not themselves need a permit. One caveat: the 2022 regulations still require a permit for demolition in article 291. The law’s letter g) came later. It is worth confirming the council’s reading before filing a demolition by declaration.

Needing a project is not needing a permit

This is a widespread confusion. Article 2.2 of the LOE, Spain’s building act, requires a project for new build and for work that alters a building’s architectural configuration. That means full interventions and partial ones that essentially change the exterior, the volume or the structural system. It also means those that change the building’s main uses. And LISTA article 138.3 expressly provides for the self-declaration to be filed «with the technical project» where one is required. Regulations article 293.2 adds that it must be stamped by the professional body where national rules require it.

So replacing the floors of an existing building on consolidated urban land needs a project, yet can go by self-declaration if footprint, height, floor area and number of dwellings stay the same. What decides the route is article 138’s conditions, not the size of the works. Where no project is needed, the declaration comes with a descriptive report and drawings.

Common cases

CommissionUsual routeWhy
Interior refurbishment of a flat without touching the structureSelf-declarationFits 138.1 a) or b). The bylaw sets the documents
Refurbishment with structural strengthening, same volume and dwellingsSelf-declaration with a project138.1 b) and 138.3
Shop to dwellingPermitIt adds a dwelling, so it falls outside 138.1 b) and f)
Shop to office, where the use is allowedSelf-declaration138.1 f), if the number of dwellings is unchanged
Extra storey or extensionPermitIt changes height, footprint or floor area
Splitting one flat into twoPermitIt adds a dwelling
New buildPermitArt. 137. Silence means refusal (regulations, art. 304.2)

The shop turned into a flat is an easy case to get wrong. We cover it in retail to residential change of use. In a protected building the law does not in itself rule out self-declaration for works, demolition aside. Article 138.4, however, requires the sectoral authorisations and reports, such as the heritage one, to be in hand first. Without them the declaration cannot be filed.

Timelines and effects of each route

Self-declarationPermitArticle
When work may startFrom the day it is filed, with complete documentsFrom notification of the permitLISTA 138.5 and 141.1
DecisionNone: checked afterwardsThree months from complete documents. Silence means approval except the cases in art. 304.2LISTA 140.2 and regulations 304
Start and completionSix months and two years, extendable by halfOne and three years unless the permit says otherwiseLISTA 141
Notify the startNot neededYes, if the works need a projectRegulations 294 b)

For a permit, if documents are missing the council allows between ten and twenty days to correct it (regulations article 301). If the technical and legal reports find curable defects, it asks once only, with no more than a month to put them right (article 302). Correction periods and sectoral reports suspend the decision deadline.

The risk in a self-declaration

A self-declaration is not an authorisation: regulations article 289.4 defines it as passing on information that allows checking afterwards. Whoever signs it states that the rules are met and that the supporting documents exist. If the works did not fit article 138 or go beyond what was declared, article 138.7 treats them as works without a permit, with enforcement and penalties to match. No declaration grants rights against the plan in force.

So the check a council officer makes for a permit is, for a declaration, made by the practice before filing it.

Before choosing the route

  • Class of land: whether it is urban and not under a transformation scheme.
  • Status of the building: in line with the plan or lawfully non-conforming.
  • Footprint and height before and after the works.
  • Floor area and number of dwellings before and after.
  • Current use, proposed use and whether the zoning bylaw allows it.
  • Whether a project is needed under LOE article 2.2 and whether stamping is compulsory.
  • Heritage protection of the building or its setting. Prior sectoral authorisations.
  • Documents and standard form the local bylaw asks for (regulations article 293.5).

The report should state this fit in writing, with the article relied on. We explain how to organise it in what a project report must contain.

How Archelo handles it

For a project in Andalusia, Archelo shows in its checks which route usually applies given the kind of works and whether they need a project. It cites LISTA articles 137 and 138 and lists the documents that go with the application. It does not decide whether the works meet each article 138 condition, nor does it know each council’s reading: the architect confirms that against the bylaw.

You can see how it works on AI for architects. This article is for information and does not replace checking the text in force of the LISTA, its regulations, any later amendments or the local bylaws that apply to the project.

Keep reading

10 · 3 · 1The years of liability for structure, habitability and finishes, counted from handover.LOE, art. 17.1

The Building Act in a practice: who answers for what and from when

Each party answers for its own part for ten, three or one year depending on the defect. Every period runs from handover, so a badly closed handover record moves the clock and leaves parts uncovered.

Ground floor plus one, seven to twelve dwellings upstairsThe decree requires the lift installed. The building code settles for leaving room for one.

Accessibility in Andalusia: Decree 293/2009 in housing projects

In a residential building, Decree 293/2009 governs communal areas and reserved dwellings, not the inside of the others. It applies alongside DB-SUA. Where the two differ, the stricter one must be met.

Art. 299.2Other authorities’ approvals come before the permit. A permit cannot be conditional on obtaining them later.LISTA Regulations

How to organise a project application before you submit it

A well-organised application prevents a missing document, an invalid signature or two figures that disagree. The council’s own list is the one that counts. Documents are sorted by when they go in: with the application, before work starts or at completion. Before signing, the same figure has to read the same in every document.

Four jobs that must be certified
  • Execution project
  • Final certificate
  • Legalisation
  • Demolition without explosives

Visado: when certification by the professional body is mandatory

Certification by the professional body is voluntary except for a closed list of work. In building, the list includes the execution project and the final certificate. The basic design is not on it and a permit can be applied for with it.

AI for architects: can it check a project against building regulations?

Software can already verify much of what a project has to state, with the article and page of every figure. What it cannot do is decide what your project means. And nothing failing does not mean it complies.

€450,759.08The contract price, with VAT, from which the study must be the full one.RD 1627/1997, art. 4.1

The basic health and safety study (RD 1627/1997): when it is enough and what it contains

Every project-based job carries a health and safety study, full or basic. Four conditions decide which. The cost threshold is measured on the contract budget with VAT, not on the material execution budget.

Seven minimum contents
  • Estimate and prevention
  • Destination and separation
  • Drawings and specifications
  • Cost

The construction waste management study (RD 105/2008): what it must include

RD 105/2008 requires the waste management study and the designer writes it. It has seven minimum contents and five of them already go in the basic design. A refurbishment adds an inventory of hazardous waste.

1.50 mThe height that most often makes usable area differ from one document to another.

The usable and gross floor area schedule: the most common mistakes

The usable area in a valuation, the one on the energy certificate and the cadastre’s gross area are not measured the same way. Countable area is set by each municipality. That is why a schedule has to say which criterion it uses.

ChatGPT for architects: what it is good for, where it fails with regulations and how to check it

ChatGPT and the other general assistants draft, summarise and explain well. They are not a source of regulations: use them for the former and never accept a requirement without opening the official text.

Documents for a building permit application in Spain: the complete file, in order and reviewed

A permit application with a project brings together five groups of documents. Each council publishes its own list, though the core is common across Spain. Before submitting, the most useful check is that they all say the same.

DB-SUA in housing: stairs, guarding and changes of level

The stair in a duplex and the communal stair are not justified with the same figures. Their balustrades are: the conditions against climbing and openings are the same throughout the building.

Refurbishment or maintenance?The first thing that decides which part of DB-SI must be justified.

DB-SI in a dwelling refurbishment: what to justify and what not

In a refurbishment DB-SI neither applies in full nor stops applying. It reaches what the work alters, escape routes if occupancy changes and protection systems if what carries them is touched. Existing safety can never be made worse.

50 l/sThe minimum extraction over the hob, with its own duct.CTE DB-HS 3

DB-HS 3: how to justify a dwelling’s ventilation rates

Table 2.1 gives the flows and the justification does not end there. Supply and extract must be balanced, openings and ducts sized and the kitchen solved. A two-bedroom flat shows how.

What a project report must contain under Spain’s building code and how to review it before submission

The report is where a project is justified. Spain’s building code sets its minimum content. What must be written depends on the work, the use, the stage and the council.

Is it allowed? Does it comply? Does the building permit it?The three questions of a shop-to-dwelling change, in order.

Retail to residential: what to check before applying for the permit

Changing a shop’s use is work that needs a project, however small it looks. The first question is not the building code but the plan: if housing is not allowed on that floor and that street, no project will do.

How to use AI in an architecture practice: from brief to permit

When people talk about AI for architects they almost always mean images. But a project is a long chain, from brief to permit. Each stage has work you can delegate and work you cannot.

40% · 20%The national minimum reserve: on rural land being urbanised, and on urbanised land under renewal.TRLSRU, art. 20.1.b

Affordable housing reserve: what to check before fixing the percentage

The national Land Act sets a minimum of 40% or 20% depending on the development. Regional law, the current plan and transitional provisions can change that figure on each site.

Pilot programme

Try Archelo on a real case.

Archelo helps you prepare all your project documents, analyses the drawings, tells you whether it complies before you submit and keeps everything organised. Want to try it?

Watch the demo

Request access

Try Archelo on your own projects. Fill in the form and we will email you as soon as your access is ready.

We use these details only to give you access.