The basic health and safety study (RD 1627/1997): when it is enough and what it contains
Every project-based job carries a health and safety study, full or basic. Four conditions decide which. The cost threshold is measured on the contract budget with VAT, not on the material execution budget.

In this article
The short version
The basic health and safety study is, together with the waste study, an annex that gets copied from one project to the next. Before opening the template, it is worth asking whether a basic study is enough for this job. We follow the consolidated text of Royal Decree 1627/1997 in Spain’s official gazette and the technical guide by INSST, the national occupational safety institute. That guide is not binding.
When the full study is required
Article 4.1 requires the client to commission the full health and safety study when any of these conditions applies. If none does, article 4.2 requires the basic study. No project-based job goes without one or the other:
| Condition | Threshold | How it is checked |
|---|---|---|
| a) Budget | Contract execution budget of 75 million pesetas (€450,759.08) or more | Contract budget = (construction cost + overheads + profit) × (1 + VAT), per the INSST guide |
| b) Duration and workforce | More than 30 working days and, at some point, more than 20 workers at once | Both conditions together, on the planned programme |
| c) Labour volume | More than 500 working days summed across all workers | Workers × days for each phase, added up. One day is an 8-hour shift |
| d) Type of work | Tunnels, galleries, underground conduits and dams | Always, whatever the budget |
It is easy to go wrong on the first condition: comparing the bare construction cost with the threshold. The decree refers to the contract execution budget. The INSST guide makes clear it includes VAT. A job under €450,000 in construction cost can clear the threshold comfortably once overheads, profit and VAT are added.
The guide adds a recommendation: the project should state the budget, the duration and the labour volume. When the basic study is chosen, it should justify with those figures why the full one does not apply. It also notes that the client can commission the full study even where the basic one would do, if the job calls for it.
Two worked examples
We take overheads of 13% and contractor’s profit of 6%, common figures that each project sets. VAT is 21% for simplicity: the applicable rate depends on the job and is worth checking.
| Job | Construction cost | Contract budget | Estimated labour | Study |
|---|---|---|---|---|
| Full refurbishment of a flat | €120,000 | 120,000 × 1.19 × 1.21 = €172,788 | 3 workers × 20 days + 5 × 40 + 4 × 30 = 380 days | Basic: no condition is met |
| Six-flat building | €400,000 | 400,000 × 1.19 × 1.21 = €575,960 | No need to work it out | Full: above the budget threshold |
In the second case the construction cost is below €450,759.08. That is why a basic study can easily slip in where the full one was due. In the first, a labour-heavy refurbishment with a long programme can approach 500 days even on a modest budget: it is worth adding it up phase by phase and putting the sum in writing.
What the basic study must contain
Articles 6.2 and 6.3 set the content of the basic study, which is much shorter than the full one (article 5.2). Comparing them makes clear what can be left out and what cannot:
| Content | Full study | Basic study |
|---|---|---|
| Health and safety rules applicable to the job | Yes | Yes |
| Avoidable risks and the technical measures to avoid them | Yes, in the report | Yes |
| Risks that cannot be removed, with preventive measures, protection and an assessment of how well they work | Yes, in the report | Yes |
| Specific measures for Annex II work | Yes, with the areas located | Yes, where relevant |
| Provisions for later work | Yes | Yes |
| Procedures, equipment and site plant. Welfare facilities | Yes | Not required |
| Specifications, drawings, measurements and budget | Yes, with the budget as a chapter of the main one | Not required |
The INSST guide describes the basic study as a purely descriptive document. It asks for enough detail that the contractor can write its plan from it. It accepts added drawings where they help. A generic list of risks from any job does not do that: the basic study has to talk about this job, its access, its surroundings, its structure and the phases it will actually have.
Special risks and later work
Two sections of the basic study are often dispatched with a stock phrase. They are the ones that say most about the job. The first is Annex II work, a non-exhaustive list of work with special risks. In building work these come up most:
- Especially serious risks of burial, collapse or falls from height: excavations, roofs, façades, slabs being demolished.
- Exposure to especially serious chemical or biological agents: in a refurbishment, typically asbestos cement, which has its own rules as well.
- Work near high-voltage power lines.
- Assembly or dismantling of heavy prefabricated elements.
The second is the provision for later work (article 6.3): how the façade will be cleaned, the roof inspected or the services maintained safely. If the project leaves a roof with no access or anchor points, the study has to say so. Making sure the report and the basic study describe the same job is part of the cross-check covered in what a project report must contain.
Who signs it and what comes next
It is written by the competent professional the client appoints. Where several designers are involved, the client must appoint a health and safety coordinator for the design stage, who writes it or has it written (articles 3.1 and 6.1). The rest of the path is as follows:
- Project: the study is part of the construction project. Including it is a condition for certification by the professional body and for the permit (article 17). Annex I of the building code lists it among the report’s annexes without an asterisk: it is not among the minimum contents of the basic project. So if the permit is applied for with the basic project, that project need not include it. Some councils ask for it with the application, so check their list. Either way, work cannot start without the construction project and its study.
- Plan: each contractor develops it into its own health and safety plan according to how it will carry out the work, without lowering the levels of protection (article 7.1).
- Approval: the construction-stage coordinator approves the plan before work starts. Where no coordinator is needed, because a single firm works on site with no self-employed workers, the site supervision team takes this on (article 7.2).
- Opening: the contractor notifies the labour authority of the opening of the site before work starts, with the plan attached (article 19). The client’s old prior notice was repealed in 2010.
- Incident book: supplied by the professional body of whoever approves the plan and kept on site at all times (article 13).
How this annex fits with the rest of the application is covered in documents for a building permit application.
Before you submit it
A pass over the study and the documents it is checked against:
- The project states the contract budget, the programme and the labour volume. It uses them to justify that the basic study is enough.
- The threshold has been compared with the contract execution budget, VAT included, not with the bare construction cost.
- Job name, site, client and phases match the report and the programme.
- The risks and measures belong to this job: its access, surroundings, structure and demolitions.
- Any Annex II work is identified with its specific measures.
- If the report or the waste study mention asbestos, so does the basic study.
- There are provisions for later work on the roof, façade and services.
- Where several designers are involved, the design-stage coordinator is named.
If it comes from a template, it is worth searching the text for any trace of the previous job: a tower crane in a flat refurbishment or a basement that does not exist gives the study away on first reading.
Where Archelo helps
Archelo recognises the health and safety study among the application’s documents, even when it sits inside the same PDF as the project. It warns when it is missing for the stage and type of work. It does not decide whether a basic study is enough, nor write it: each job’s budget, programme and risks are known by whoever designs it. You can see how it works on AI for architects.
This article is for information only and does not replace checking the current text of Royal Decree 1627/1997 and the rules that complement it, nor what the professional body and the council require for each job.